[vc_row][vc_column][vc_column_text]Fourth quarter was a busy quarter for installations for the Los Angeles Branch.
Customer “A” – In Suite #1, the customer requested that we remove the existing ductwork and install new ductwork for their three Kwikool units and one 10-ton Liebert unit. In Suite #2, we removed one existing 20-ton Liebert unit and installed two new 10-ton Stulz units. We provided temporary cooling, and ductwork to keep their cold aisle cool during the installation of the new units. We removed the 20-ton unit by cutting it into four sections to remove it from the suite. We also modified the existing ductwork in their space for the two 10-ton Stulz Units. Sometime in 2021, the customer is planning to have DP Air Corporation remove the remaining 20-ton Liebert in suite 1611 and install two new 10-ton Stulz units.
Customer “B” – We installed a slightly used UPS, PDU and ATS switch at one of our Mattel sites during the 4th quarter. When we installed the UPS, PDU and ATS the install took place within the 8-hour window that the customer required in their critical space. Two up-flow DS units and condensers are scheduled to be installed in the 1st quarter of 2021, as long as city and permits allow.[/vc_column_text][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][vc_single_image image=”13964″ img_size=”full”][/vc_column][vc_column width=”1/2″][vc_single_image image=”13965″ img_size=”full”][/vc_column][/vc_row]